Bearspaw South Feeder Main Construction Progress Continues with 80% of Replacement Steel Pipe Installed

The Bearspaw South Feeder Main Replacement Project continues to advance on schedule, with approximately 80 per cent of the new feeder main pipe now installed in the ground across Stages A and B.“We are pleased to have more than 90 per cent of the project materials required to complete the project on-site in Calgary, including 93% for the steel pipe,” said Darren Finney, Manager, Major Projects. “Crews continue to make strong progress across both stages, and we remain on track for the new f

City of Calgary Newsroom · Sep 24, 2026